Single-Machine Sequencing by Due Date
Single-machine sequencing by earliest due date, which minimises the maximum lateness.
납기순 단일 기계 일정 — 최대 지연을 최소화하는 납기순(EDD)으로 단일 기계 일정을 정합니다.
Runs Machine scheduling calculator with: problem set to “single_machine”; rule set to “edd”.
기본 방법(Machine scheduling calculator)에 다음 설정을 고정해 실행합니다: problem = single_machine; rule = edd.
In what order should I do these jobs so the latest one is as little late as possible?
가장 늦는 작업이 최대한 덜 늦도록 하려면 어떤 순서로 해야 하나요?
EDD sorts by due date and is optimal for maximum lateness. Behind it is the Machine scheduling calculator with problem = single_machine, rule = edd set; the other inputs work as usual.
When to use Single-Machine Sequencing by Due Date
- One machine or resource.
- Due dates matter.
When to use something else
- Number of late jobs matters; use Moore–Hodgson.
- You want to compare this setting with the alternatives; run the Machine scheduling calculator with each option.
What you still provide
- Data: the summary numbers the calculator asks for; no data file.
How this is validated
검증 근거
This preset fills in settings of the Machine scheduling calculator; the calculation is that calculator’s. No separate checks of this preset are claimed.
이 설정 묶음은 Machine scheduling calculator의 설정을 채워 둔 것입니다. 계산은 그 계산기와 같으며, 이 설정만 따로 검증했다고 주장하지 않습니다.
Other variants of Machine scheduling calculator
- Flow-Shop Sequencing (CDS Heuristic)
- Flow-Shop Sequencing (NEH Insertion)
- Single-Machine Sequencing by Weighted Shortest Time
- Single-Machine Sequencing to Minimise Late Jobs
- Two-Machine Flow-Shop Sequencing (Johnson's Rule)
Run this variant
- Data you need
- the summary numbers the calculator asks for; no data file
- Price
- Free in the browser calculator; no credits are used.
- Checking
- Uses the same calculator as the Machine scheduling calculator; no separate validation record is published for this preset.